What are the potential impacts for the community during the construction of the Itivia project?

The Itivia project will generate disturbance such as increased traffic, noise, dust and vibration. During the construction and operation stage, sensory disturbances to wildlife may occur. The construction activity will also create an inconvenience for those individuals wanting to use the boat launch

2017-07-14T17:40:36+00:00July 14th, 2017||Comments Off on What are the potential impacts for the community during the construction of the Itivia project?

What will generate noise during the construction?

During construction, noise will be generated primarily from increased traffic, drilling, crushing and blasting activities. The Rankin Inlet baseline is between 54 to 64 dB in the daytime and 45 to 52 dB at night. Noise levels are anticipated to increase a maximum of 6 decibels above the actual Rankin Inlet baseline. The noise should [...]

2017-07-14T17:41:09+00:00July 14th, 2017||Comments Off on What will generate noise during the construction?

Where will the vibrations come from?

Vibrations will result from quarry blast expected to occur 2-3 times per week. Little or no vibrations have resulted from Laydown area blasts that occurred in May and June. All blasts are monitored for vibration using seismometers. There are 5 seismometers located in the neighbourhood near Itivia

2017-07-17T15:15:56+00:00July 14th, 2017||Comments Off on Where will the vibrations come from?

What has Agnico planned to mitigate dust issues?

Agnico is working with the Hamlet to help minimize dust issues All Agnico vehicles must adhere to a speed limit of 15km/hr The crusher is equipped with a bag house and is located in an area to minimize dust emissions. Loading, hauling and placing of materials and sea cans are not expected to generate dust [...]

2017-07-14T17:42:31+00:00July 14th, 2017||Comments Off on What has Agnico planned to mitigate dust issues?

What will traffic be like within the community boundaries?

The containers as well as other equipment pieces are transported by trucks from the Itivia area to the Meliadine mine site; The transfer of all the material from the Itivia harbour to the mine site will be done on a 14 hours/day schedule between the hours of 6:00 am and 8:00 pm.

2017-07-17T15:14:41+00:00July 14th, 2017||Comments Off on What will traffic be like within the community boundaries?